Power lines in Austria for APG

requirements

Since 2021, we have been working on the construction of an important 380kV power line on the Alps of Salzburg. As per the project designed by APG (Austrian Power Grid), the work is to be completed in 2024. 

The project included

  • Excavations
  • Reinforced concrete constructions
  • Soil nailing
  • Spritz beton
  • Micropiles
  • Self-drilling bars

Standard or extreme operational mode

Exstreme

Duration of the work

3 years

Challenges

The mountain site is inaccessible.

Solutions

To handle the logistic and transportation challenges and reach the construction site we make use of special machinery that can be dissembled and transported via helicopter.

Noteworthy technical details

The operations in question are complex and require professionalism and precision. We installed satellite instruments on our operating machinery.